Particulars | Details/Status |
---|---|
Project Name | Four Laning of existing 2- lane stretch from Govindpur (MH/TG Border) (Design Km.32.910) to Rajura Border (Design Km.89.090) {Design Length – 56.180 Km.} section of NH-353B in the State of Maharashtra on Hybrid Annuity Mode under NH (O) |
Concessionaire Name (SPV) | G R Govindpur-Rajura Highway Private Limited |
Concessionaire’s Contractor Name (Parent Company) | G R Infraprojects Limited |
Independent Engineer | M/s. Theme Engineering Service Pvt. Ltd. In association with M/s Ishita Info Solution Pvt. Ltd. |
Date of Award (LOA Date) | 30-March-2022 |
Agreement Signing Date | 17-May-2022 |
Appointed Date | 17-October-2022 |
Construction Period (in Days) | 730 Days |
Total Concession Period (In Years) | 15 Years + Construction Period of 730 Days |
Scheduled Date of Completion | 15-10-2024 |
Mode of the Execution | Hybrid Annuity Mode (HAM) |
No. of Lanes / Configuration | 4 Lane |
Length of the Project (in Km) | 56.180 Km (MCW) |
Total Project Cost (in Cr.) | 907.00 Cr. |
No. of Major Bridges | 01 No. |
No. of Minor Bridges |
28 Nos.+(01 COS) |
No. of Toll Plazas | 01 No. |
No. of Flyovers/Elevated structure | 01 No. |
No. of Rest Area | 01 No. |
No. of Truck Lay-bays | 01 No. |
No. of Box Culverts | 76 No. |
No. of (VUP/LVUP) | 04 Nos. |
AUP | 08 Nos. (3 nos Merged to AUP/MJB at Ch. 88+108) |
HPC |
52 Nos. |