Project Milestone Status

Project Milestones Status

Milestone As per Contract Agreement Actual Delay (No. of Days) if any Current Status Remarks (Letter or comment Ref., if any)
Days from Appointed Date Physical Progress (%) Scheduled Date Physical Progress (%) Actual Date
Milestone-I 160 20.00% 25-Apr-2023 20.63% 17.06.2023 Achieved Concessionaire Letter GRGRHPL/GORA1/SITE/406 dated 19.06.2023

IE Letter No. 1084, dated 20.06.2023

Milestone-II 360 35.00% 12-Oct-2023 35.02% 05.01.2024 Achieved Concessionaire Letter GRGRHPL/GORA1/SITE/705 dated 09.01.2024

IE Letter No. 232, dated 19.01.2024

Milestone-III 500 75.00% 29-Feb-2024 75.10% 31.01.2025 Achieved Concessionaire Letter GRGRHPL/GORA1/SITE/1342 dated 14.02.2025

IE Letter No. 651, dated 17.02.2025

Schedule Completion Date 730 100.00% 16-Oct-2024   Physical progress till 28.02.2025 is 82.87%. Revised date is 18.08.2024 for PM-III and 05.04.2025 for Scheduled Completion Date (Authority letter 962 dated 16.10.2024)