Project Milestone Status

Project Milestones Status

Milestone As per Contract Agreement Actual Delay (No. of Days) if any Current Status Remarks (Letter or comment Ref., if any)
Days from Appointed Date Physical Progress (%) Scheduled Date Physical Progress (%) Actual Date
Milestone-I 160 20.00% 25-Apr-2023 20.63% 17.06.2023 Achieved Concessionaire Letter GRGRHPL/GORA1/SITE/406 dated 19.06.2023 IE Letter No. 1084, dated 20.06.2023
Milestone-II 360 35.00% 12-Oct-2023 35.02% 05.01.2024 Achieved Concessionaire Letter GRGRHPL/GORA1/SITE/705 dated 09.01.2024 IE Letter No. 232, dated 19.01.2024
Milestone-III 500 75.00% 29-Feb-2024 63.66% In progress
(EOT Proposal submitted)

Physical progress till 31.10.2024 is 63.66%. Revised date as per Settlement Agreement dated  is  18.08.2024 for PM-III and 05.04.2025 for Scheduled Completion Date

Schedule Completion Date 730 100.00% 16-Oct-2024