Milestone | As per Contract Agreement | Actual | Delay (No. of Days) if any | Current Status | Remarks (Letter or comment Ref., if any) | |||
---|---|---|---|---|---|---|---|---|
Days from Appointed Date | Physical Progress (%) | Scheduled Date | Physical Progress (%) | Actual Date | ||||
Milestone-I | 160 | 20.00% | 25-Apr-2023 | 20.63% | 17.06.2023 | – | Achieved | Concessionaire Letter GRGRHPL/GORA1/SITE/406 dated 19.06.2023 IE Letter No. 1084, dated 20.06.2023 |
Milestone-II | 360 | 35.00% | 12-Oct-2023 | 35.02% | 05.01.2024 | – | Achieved | Concessionaire Letter GRGRHPL/GORA1/SITE/705 dated 09.01.2024 IE Letter No. 232, dated 19.01.2024 |
Milestone-III | 500 | 75.00% | 29-Feb-2024 | 63.66% | – | – | In progress (EOT Proposal submitted) – |
Physical progress till 31.10.2024 is 63.66%. Revised date as per Settlement Agreement dated is 18.08.2024 for PM-III and 05.04.2025 for Scheduled Completion Date |
Schedule Completion Date | 730 | 100.00% | 16-Oct-2024 | – | – | – |